Workplace Charging Scheme (WCS) 2026: Full Guide

Last updated: June 2026. Grant rates reflect OZEV guidance current as of 1 April 2026.

The Workplace Charging Scheme (WCS) is the UK's primary government grant for businesses, charities, and public sector organisations installing EV charge points for staff and fleet vehicles. Administered by OZEV, the WCS provides up to £500 per socket, capped at 40 sockets (£20,000) per applicant. See our EV Charger Grants for Businesses hub for a full overview of business grant options.

From 1 April 2026, the WCS also includes an enhanced rate for state-funded education institutions: up to £2,000 per socket. This guide covers the standard WCS rate. For the education rate, see the WCS for Education guide.

Want to apply? Contact Blink Charging for a free site assessment.

Workplace Charging Scheme at a Glance

What it isA government grant for businesses, charities, and public sector bodies to buy and install EV charge points for staff and fleet vehicles.
Who it is forUK businesses, charities, public sector organisations, and sole traders with a business premises.
Funding availableUp to £500 per socket. Maximum 40 sockets per applicant (£20,000 total) per financial year.
Key requirementsStaff/fleet use only. OZEV-approved installer. Valid WCS voucher before installation begins.
Scheme statusOpen. Extended until 31 March 2027.

Education Rate

State-funded schools, colleges, and universities receive up to £2,000 per socket (max 40 sockets, £80,000 total).

Who Can Apply for the Workplace Charging Scheme?

The WCS is available to a wide range of UK organisations with a business premises where charge points will be used by employees or fleet vehicles.

Eligible organisations

  • Private limited companies and PLCs

  • Partnerships and LLPs

  • Sole traders and self-employed individuals with a business premises

  • Charities and not-for-profit organisations

  • NHS trusts, local authorities, and other public sector bodies

  • State-funded schools, academies, colleges, and universities (enhanced rate applies)

  • Housing associations (for staff use)

Key eligibility conditions

The applicant must be registered in the UK with a business premises address.

Charge points must be for employee or fleet vehicle use, not for general public charging.

The installation must be carried out by an OZEV-approved installer.

A valid WCS grant voucher must be issued by OZEV before installation begins.

What Does the Workplace Charging Scheme Fund?

The WCS grant covers the cost of buying and installing eligible EV charging points at your business premises, including the charge point unit, installation labour, and associated cable works to the distribution board.

The grant does not cover ongoing electricity costs, network management fees, civil engineering groundworks, or charge points intended for public use or customer charging.

How Much Can You Claim?

The standard WCS rate from 1 April 2026 is up to £500 per socket. The maximum is 40 sockets per applicant, giving a maximum of £20,000 per financial year. For state-funded education institutions, the rate rises to £2,000 per socket. See the WCS for Education guide for details.

Multi-site businesses: the 40-socket cap applies per legal entity, not per site. If your business operates from multiple premises under the same company registration, the 40-socket maximum applies across all sites combined.

How to Apply for the WCS

Contact Blink Charging for a free site assessment covering your power supply, parking layout, and EV charging requirements.

Your installer submits the WCS voucher application to OZEV. You will need to provide basic information about your organisation and premises.

OZEV issues the WCS grant voucher, typically within 2 to 4 weeks. Installation cannot begin until the voucher is issued.

Your installer completes the installation. The grant is deducted from your invoice.

Choosing the Right Charge Point

The charge point must be on the OZEV-approved products list and must be a smart charge point. Blink Charging's workplace charge points are OZEV-approved and fully supported by our network management platform. For most workplaces, a 7kW AC charge point per bay is the most cost-effective solution. Get in touch to discuss the right specification for your site.

Frequently Asked Questions

Can I apply for the WCS if I already have some charge points installed?

Yes. The WCS applies to new installations only. You cannot retrospectively claim for charge points already installed.

WCS vouchers are valid for 180 days from the date of approval. Contact your installer immediately if you cannot complete within this period, as OZEV may grant an extension in certain circumstances.

Yes. Registered charities are eligible for the standard WCS rate of £500 per socket, up to 40 sockets. The charity must have a UK business premises and the charge points must be for staff or volunteer vehicle use.

No. The WCS applies to England, Scotland, Wales and Northern Ireland only.